HS2 contractors wheel in second Solihull bridge
Contractors on the HS2 project have installed the second of four new bridges planned for Solihull to reconfigure the road network around the new interchange station
The 914-tonne structure was constructed at the side of the road and then wheeled into place using 64 axle-lines of self-propelled modular trailer (SPMT).
It took just 45 minutes to move the 150-metre span structure into alignment and lower it onto the prepared abutment shells.
Video uploaded on 26/10/2020 12:00am.